ĐT975 – hành lang sân bay Phú Quốc

Ended · Tue, Oct 6, 12:34 PM ICT

This event has ended.

See what's on next →

ĐT975: 10-lane boulevard + ~18km LRT linking airport–APEC (24/7 construction) (ended)

ĐT975 → ~62 m boulevard: 10 lanes + median LRT, PQ airport–APEC centre. Early Sep 2026: trenches ~65%, drainage ~50%, road bed ~50%; 4 bridges >55%. LRT ~17.59 km double track, rails in ~6 months. 3 shifts 24/7. Drivers: obey temp diversions on airport–APEC corridor.